Panther Creek

When GE was awarded the O&M contract for the Panther Creek I, II and III windfarms, they called ANEMOI to perform the pitch battery replacements on the 305 turbines at the sites. The project was planned for 12 weeks, however, the ANEMOI team deployed three crews and worked for two months, six-days-a-week, to perform the exchanges. Each crew performing an average of two towers per day, and allowed the work to come in under budget and under schedule.